Govt Clarifies Lahore–Sahiwal Motorway Cost and Approval

January 12, 2026Zayn0

Media Reports Question Rs465 Billion Lahore–Sahiwal Motorway

Federal Planning Minister Ahsan Iqbal has issued a clarification after media reports claimed that the federal government had conditionally recommended a costly provincial motorway scheme in violation of fiscal rules and prime ministerial directives. The reports alleged that the Central Development Working Party (CDWP) had pushed forward a Rs465 billion Lahore–Sahiwal–Bahawalnagar motorway project despite questions over funding, design and compliance with the National Fiscal Pact.

Those reports also claimed that the revised motorway cost was about Rs201 billion higher than estimates prepared two years earlier. Commentators warned that such a large road investment might draw traffic and funding away from the Mainline-I (ML-I) railway upgrade under the China–Pakistan Economic Corridor (CPEC).

What the CDWP Actually Approved on 6 January 2026

In his statement, Ahsan Iqbal said the issue was discussed in detail during a meeting of the CDWP held on 6 January 2026. He stressed that the forum did not approve the full 295 km Lahore–Sahiwal–Bahawalnagar motorway as reported. Instead, he explained, the CDWP only recommended an already approved 18.5 km section of the scheme—stretching from Lahore Ring Road at Hallok to the Raja Jhang Interchange on Kasur Road—for consideration by the Executive Committee of the National Economic Council (ECNEC).

Iqbal clarified that the remaining 276.5 km of the proposed motorway alignment had not been granted final approval. The CDWP, he said, directed the relevant agencies to first complete detailed technical feasibility and economic viability studies before any further decision is made. This includes re-examining traffic forecasts, route alignment options and the broader economic impact of the project on existing transport corridors.

Financing Limits, PPP Options and Competing PSDP Priorities

The planning minister underlined that Pakistan is operating under tight fiscal constraints, particularly within the Public Sector Development Program (PSDP). For this reason, the CDWP instructed the Ministry of Communications and the National Highway Authority (NHA) to explore alternative financing arrangements for the motorway, including public–private partnership (PPP) models and contributions from the provincial government. The aim, he said, is to ensure that scarce federal resources are not overstretched.

Iqbal argued that relying heavily on PSDP funds for a large provincial motorway could crowd out other critical schemes already in the pipeline. He pointed to projects such as the Sukkur–Hyderabad Motorway, realignment of the Karakoram Highway, dualisation of the N-55, electrical and mechanical works of the Lowari Tunnel, the Khyber Pakhtunkhwa Economic Corridor, the Pakistan Expressway linking Karachi and Chaman, and the Hoshab–Khuzdar Road as examples of competing priorities.

Concerns Over ML-I, Fiscal Rules and Project Costing

Responding to claims that the CDWP had ignored the National Fiscal Pact, Iqbal said the forum had only granted in-principle approval to the remaining motorway components. This provisional nod, he explained, was based on assurances from the NHA that it would seek financing through PPP structures and provincial contributions rather than relying purely on federal PSDP allocations. Any final approval, he added, would still depend on meeting codal requirements and completing feasibility studies.

He noted that the project’s alignment would also have to be finalised in line with the prime minister’s directives so that new motorway investments complement, rather than clash with, national transport plans. Earlier Planning Commission comments had cautioned that the original proposal might affect ML-I’s viability and relied on outdated construction rates.

Iqbal said such internal comments are a normal part of project appraisal and are meant to improve design and costing. He maintained that the CDWP respected fiscal discipline and that no final approval had been granted for the full motorway at federal expense.

Balanced Regional Development and Provincial Allocations

Addressing criticism over regional priorities, the planning minister reiterated that the federal government is committed to balanced growth across provinces. He said Balochistan has received the largest PSDP allocation at Rs206 billion, followed by Sindh with Rs154 billion, to ensure underdeveloped regions receive special attention.

He added that public debate and media scrutiny of large infrastructure projects is healthy, but argued that it must reflect what has actually been approved at each stage. In his view, the Lahore–Sahiwal–Bahawalnagar motorway remains largely at a conditional and exploratory stage beyond the 18.5 km section cleared for ECNEC review and will only move forward if it passes economic, fiscal and strategic tests.

Zayn

Leave a Reply

Your email address will not be published. Required fields are marked *

Prove your humanity: 9   +   8   =  

Search & have fun

Search anytime for whatever you need, for your business, fun or personal needs. LCCI helps you find it easy and fast.

Search & have fun

Search anytime for whatever you need, for your business, fun, or personal needs. LCCI helps you find it easy and fast.

Explore

Users

LCCI

Copyright © 2025 LCCI  All Rights Reserved.
Developed by TARGET MARKETING (PVT) LIMITED

Copyright © 2025 LCCI  All Rights Reserved.
Developed by TARGET MARKETING (PVT) LIMITED.