Punjab’s Rs39bn Plan to Modernise 485 Villages by December 2026

June 10, 2026Zayn0
Development Desk | June 2026 | 4 min read

 

⚡  QUICK TAKEAWAYS
•       485 villages across Punjab are being developed under the model villages programme, targeting four million residents.
•       An additional Rs39 billion is under consideration for the next phase, on top of current first-phase funding.
•       Local Government Minister Zeeshan Rafique has set December 2026 as the completion deadline for the first phase.
•       Infrastructure works include paved streets, restored ponds, children’s parks, streetlights, and targeted water supply schemes.
•       CM Maryam Nawaz has directed expansion of the programme to 7,500 villages in future phases.

 

Punjab is pressing ahead with one of its most ambitious rural development programmes, with officials reviewing a fresh Rs39 billion allocation to fund the next phase of the model villages initiative. The first phase, targeting 485 villages across all ten divisions of the province, is now being pushed toward a December 2026 completion deadline — with an eventual ambition to reach 7,500 villages across the province.

 

485

Villages — Phase 1

across 10 divisions

4 Million

Beneficiaries

first phase target

7,500

Villages — Long Term

CM Maryam’s directive

 

What the Programme Delivers

Under the model villages programme, selected rural settlements are to receive a package of municipal upgrades that have historically been available only in urban areas. Every street in participating villages will be paved. Traditional ponds — a feature of Punjab’s rural landscape that have fallen into disrepair across many areas — are to be restored. Children’s parks and functional streetlighting are also included in the standard works package.

Water supply schemes are part of the programme but come with a caveat introduced at the Civil Secretariat meeting: Minister Zeeshan Rafique instructed that water infrastructure should only be included in villages that actually face water shortages. The instruction reflects a concern about wasteful spending — installing water schemes in areas that do not need them would inflate costs without delivering commensurate benefit. Similarly, the minister directed officials not to break already paved streets unnecessarily during implementation.

🏛️  PROGRAMME OVERVIEW

The programme operates under the brand name Maryam Nawaz Ka Sohna Punjab (Maryam Nawaz’s Beautiful Punjab), the flagship rural development initiative of Chief Minister Maryam Nawaz. The Punjab Rural Municipal Services Company is the implementing body responsible for on-the-ground progress and briefing senior officials.

 

Division-Wise Village Breakdown

Division Villages Included Share of Programme
Multan 63 13.0%
Rawalpindi 58 12.0%
Gujranwala 55 11.3%
Gujrat 51 10.5%
Lahore 50 10.3%
Sahiwal 44 9.1%
Sargodha 41 8.5%
DG Khan 39 8.0%
Faisalabad 36 7.4%
Bahawalpur 48 9.9%
TOTAL 485 100%

 

The Rs39 Billion Next-Phase Proposal

Officials are currently reviewing an additional allocation of Rs39 billion for the programme’s subsequent phases. This figure is under consideration and has not yet been formally approved. The review reflects a strategic decision to plan the next phase before the first is complete — allowing lessons from implementation to inform how resources are deployed across a larger number of villages.

Minister Rafique specifically directed that planning for future phases draw on the experience and challenges of the first phase. This is a recognition that large-scale rural infrastructure programmes in Pakistan have historically suffered from poor sequencing, with later phases repeating mistakes from earlier ones. Building a feedback loop between the first and subsequent phases is intended to prevent that pattern.

Long-Term Vision: 7,500 Villages

The scale ambition behind the programme is significant. Chief Minister Maryam Nawaz has directed that the model villages initiative ultimately expand to cover 7,500 villages across Punjab — roughly fifteen times the coverage of the current first phase. Punjab has approximately 25,000 villages, meaning a 7,500-village programme would bring modern municipal services to nearly a third of the province’s rural settlements.

The jump from 485 to 7,500 villages will require sustained multi-year funding commitments, institutional capacity at the Punjab Rural Municipal Services Company, and coordination across all provincial divisions. The December 2026 deadline for the first phase serves as the initial proof of concept — if 485 villages can be delivered on time and to specification, the case for scaling becomes considerably stronger.

📊  DIVISION ALLOCATION NOTE

The distribution across divisions is broadly proportional to rural population but shows some variation. Multan leads with 63 villages, while Faisalabad — one of Punjab’s most industrialised divisions — has the lowest allocation at 36. Rawalpindi’s 58 reflects both population size and the government’s focus on peri-urban rural areas around the capital region.

 

Disclaimer: This article is based on official statements from the Punjab Local Government Department and related reporting. The Rs39 billion additional allocation is under review and has not yet been formally approved. Project timelines and village counts are subject to revision.

Zayn

Leave a Reply

Your email address will not be published. Required fields are marked *

Prove your humanity: 3   +   3   =  

Search & have fun

Search anytime for whatever you need, for your business, fun or personal needs. LCCI helps you find it easy and fast.

Search & have fun

Search anytime for whatever you need, for your business, fun, or personal needs. LCCI helps you find it easy and fast.

Explore

Users

LCCI

Copyright © 2025 LCCI  All Rights Reserved.
Developed by TARGET MARKETING (PVT) LIMITED

Copyright © 2025 LCCI  All Rights Reserved.
Developed by TARGET MARKETING (PVT) LIMITED.